Wandoan, Qld

Reidy Constructions

The Challenge

The project required a storm water package pump station, to be located under a unit development driveway.

The Solution

  • Australian Tanks provided a 20kPa load rated precast concrete tank that was designed to be trafficable by a fully loaded semi-trailer
  • The pump equipment, including all the pipework, valves, upper guide bar brackets, guide rails, discharge connections, pumps, pump lifting chains, and float switches, were fitted in the tank in the Australian Tanks factory

The Results

  • A complete package pump station was delivered to site that could be placed straight into the excavation
  • The electrical and plumbing connected and be ready for immediate service

Products

  • One (1) Australian Tanks 25,000L 20kPa load rated
  • Precast anti-floatation concrete tank
Enviro Pacific
Enviro Pacific, contractor for a new 7Eleven fuel station at The Gap (Qld), contracted Australian Tanks (ATQ) to supply a 20,000L trafficable and anti-floatation blind sump tank to capture stormwater run-off contaminated with fuel from the area ssurrounding fuel bowsers. With no tank specified on the plans, Enviro Pacific sought a solution which met all industry standards and one which would be approved by 7Eleven.
Hutchinsons Builders
With stormwater run off from surrounding sites, a rapid install was essential. Combined with budget constraints, a cost efficient solution was required for project maximisation.
Accurate Plumbing
Previously, Accurate Plumbing (the Plumbing Contractor) had installed up to 30 pump stations using an alternative system over a 12-18 month period. The pump stations were challenged with speed issues and OHS requirements, further impacted by the cost and time loss incurred by ongoing replacement and servicing.
Reidy Constructions
Australian Tanks provided a 20kPa load rated precast concrete tank that was designed to be trafficable by a fully loaded semi-trailer.
The pump equipment, including all the pipework, valves, upper guide bar brackets, guide rails, discharge connections, pumps, pump lifting chains, and float switches, were fitted in the tank in the Australian Tanks factory.

All our product specs any time.

Are you planning for an upcoming project? Our Engineer’s Hub can help you find the product you need, quickly and easily.

Every detail is here for you when you need it, at your own leisure, to help you discover what is the right fit for your project.

Gain access to all the required plans to determine which product meets your needs and be able to specify the solution into your design with downloadable CAD drawings.

Complete access to all our documents